Tuesday, September 26, 2006

Money To Burn ?

RUMOURS OF A HANSON TAKEOVER BY CEMEX

The financial papers have recently been full of rumours of a 6.3 BILLION POUND Cemex takeover of the Hanson building and aggregates company, which has a large market share in the USA, and the UK. In the UK any acquisition would probably fall foul of the anti trust laws, and be regulated.

The suggested price is £6.3 billion, more than DOUBLE the $5.8 million price tag Cemex paid last year for RMC.

So the Warwick Court Recorder need not overly worry himself over the size of the Cemex piggy bank! They obviously have money to burn and the anticipated fine, to be imposed on 3rd October, will no doubt just be "small change" for these guys!

UNDER FIRE CEMENT FIRM BLASTED AGAIN

COMPLAINTS: Campaigners appalled by new figures on Rugby plant - says

Evening Telegraph 25 September.

Critics hit out against Cemex today after new figures revealed the factory had been investigated 25 times in the past 3 years. The new figures showing the Rugby Cement factory had one suspected breach of Environment Agency regulations every 6 weeks follows a Freedom of Information request by the Evening Telegraph. In a statement an Environment Agency spokesman said "In the last three years there are a total of 25 incidents on our system which have led to justified complaints. For 7 of these 25 incidents we have received multiple complaints."

Lilian said "It is terrible. 25 incidents might sound not like a lot to some people but this is just the tip of the iceberg. The EA gives them a good "Operator Score" (OPRA) but their compliance level is very low. That means Cemex wheedles their way into the Agency's good books and then the Agency does not regulate them as much. Then it is a case of 'while the cat's away the mice will play'."

Earlier this month the plant was named in a pollution black list in the environmental journal ENDS report. In August the company pleaded guilty at Warwick Crown Court to breaching regulations set down in the company's operating regulations. The breach followed a fallout of dust from its factory in October last year. Cemex is due to be sentenced at Warwick Court on 3rd October.

Sunday, September 17, 2006

SITE COMPLIANCE FAILURES

It comes as no surprise whatsover to Rugby residents to find that the Environment Agency, using the favoured "lighter touch" regarding the regulation of the Rugby Cement plant, has now discovered that the plant it rated "A" for operator performance (OPRA) has now, in reality, scored a "D" for compliance. Or should that read for non-compliance?

Poor management at industrial sites caused more than 1,700 incidents of non-compliance with permit conditions that may have led to serious harm in 2005, according to official figures. The figures are likely to have caused red faces at some sites hitherto classed as "well managed" by the Environemnt Agency.

The Health Protection Agency stated that "well-managed, well-maintained waste burning cement plants" should (hopefully) not cause any health problems for local residents. So far they have failed to give any opinion on "UNmanaged and poorly-maintained cement plants" which are very much the "norm", and that is what we seem to have here!

No surprise for guessing who tops the list of offenders! The "A" list, or should that read the "Z" list, includes:

# CEMEX Rugby and CEMEX in various locations and guises,

# Blue Circle Cement works at Aberthaw,

# Lafarge Cement Hope,

# Castle Cement.

Its about time the Authorities admitted the dangers that face the population of Rugby instead of trying to hide the facts, allay all fears, and falsely re-assure the residents with their "exaggerated" and "unsubstantiated" claims about air quality and health in Rugby.

It is the TIME for TRUTH!

Saturday, September 09, 2006

WAR RAGES ON IN RUGBY

IS THE CEMENT PLANT TO BECOME A CO-INCINERATOR – OR NOT?

The focus on the significance of the stack emissions has now moved away onto the previously hidden air quality and health impact of the Low level Sources. Rugby people require a TOTAL BURDEN figure for this plant, which has been increasing pollution year on year as production increases, and waste burning increases, and as raw materials are replaced by other wastes. The old plant was very polluting and dirty, but they closed down six dirty old kilns and built this new semi-wet process plant, (in order to replace them all), in the most ENVIRONMENTALLY DETRIMENTAL SITE of all – in the middle of a town, surrounded by vulnerable receptors in an already deprived area, with no available raw materials, no transport, no rail connections, no road connections, and no possible justification – except it was cheaper for Rugby Cement as the other real estate was worth more to them. The Environment Agency and Rugby Borough Council claim to have been party to this and helped in the design and development of this plant all along the line.

“Experts” now chew over last year’s tyre trial results as the Agency and Rugby Cemex Cement try to prove that Rugby town centre really is the Best Practicable Environmental Option for the disposal/co-incineration of waste – tyres for starters – and soon to be London’s household and commercial waste. Unfortunately for them the Jury is still out, with claims that their case is “not proven” - that not enough data has been provided, that short term impacts have been left out, that the speciation of particles (particle size and adsorbed pollutants) is missing, and that it is simply not enough to reduce the emissions of nitrogen while increasing some other hazardous pollutants.

The row goes on, and on, about the emissions from the myriad of small stacks and vents known as Low level Point Sources. The Agency claims these are regulated, but in fact only the cement mills have any limits imposed on them, and then these are not monitored or reported. It was the emissions from these 18 sources, and their HUGE environmental and air quality impacts, that the Agency and Rugby Cement were so desperate to hide from the public during the SHAM consultation into the IPPC application, which the EA and Rugby Cement and Rugby Borough Council all connived together to cunningly and falsely describe as a “Tyre Burning Application” – giving out ONLY tyre burning information, and advising the public that we could ONLY be consulted on the difference between the mains stack emissions “with coal” and “with tyres”!!

And so they hid the dispersion models of these sources, known at AQMAU 1 and AQMAU 2, and also hid the H1 assessment, which relates to the environmental assessment. When members of the public, and even the MP Andy King asked for these, they received evasive and misleading answers, and even in some cases “threatening and bullying” letters, in order to prevent any more questions from being raised.

Slowly the information is being dragged out of them, but each new report they issue contains information at variance with previous reports, so everyone is even more confused – which is what they want!! The facts are quite simple however:

1. The cement plant as built had no Environmental Statement of Environmental Impact Assessment.
2. Officers at Warwickshire County Council, under “an assumed (very convenient) delegated power” permitted the construction of a much larger plant, that had not been applied for, advertised, or consulted on. Hence the SHOCK as Rugby residents realised that, by stealth and connivance, and misinformation, a 2 million tonne a year plant was belching out massive plumes, and fumes, and dust, accompanied by 800 heavy lorries in narrow Victorian town centre streets. As described by the Agency itself, a “giant industrial behemoth” was suddenly a hideous reality.
3. The IPC Permitting process was flawed and unlawful, with the Agency and RBC conniving to hide the application and avoid the public consultation. The application was completed by Rugby Cement on 16th June 1999 and was then sent to the statutory consultees for comment, but with the proviso that “you must not tell anyone, or let any member of the public see this.” That was in order to get the IPC permit granted on 13th September 1999, “under the wire”, as by November 1st 1999 they would have had to go through the much mores stringent IPPC process for a “new plant” which would have caused outcry – and subsequently did – but then they claimed it was “an existing plant” and that the “consultation is only about tyre burning and differences in the main stack emissions!”
4. The Health Protection Agency was extremely critical of the Decision Document and IPPC Permit issued by the Agency in August 2003. They say this, amongst many other criticisms: “In our view the Decision Document is too DISSMISSIVE of HEALTH ISSUES and is NOT RFELECTIVE OF THE WIDE RANGING CONCERNS OF LOCAL PEOPLE. If you read this document you would not come to the conclusion that considerable questions have raised about the (IPPC) application, and the proposal to burn tyres. It is NOT CLEAR whether the Agency agreed or took into account all of the comments made by the statutory consultees. Many of their explanations relating to health concerns are extremely brief and NOT wholly convincing. It is also not clear why certain concerns were discussed in the Decision Document, but others concerns not? There is reference to the Agency’s state of the art dispersion model. We have yet to see any out comes of this model. It does not appear to have been made publicly available. At no point in the Decision Document do they mention that the Primary Care Trust obtained advice from the CHMRC – now the Health Protection Agency.”
5. In the IPPC permit the Agency decided NOT to ensure that BAT (Best Available Technique) was implemented, but merely to set in train a number of “Improvement Conditions”, all the time permitting the what has been described as a “state of the art” new plant to pollute Rugby residents unnecessarily. One of these conditions was that Rugby Cement should provide a “Particle Inventory for all Sources”, which OF COURSE should have been part of the IPC application in 1999. And even failing that should have been part of the 2001 IPPC application. However the Agency chose to HIDE its own January 2003 report (AQMAU) and allow Rugby Cement a further 2 years in which to produce the report. It was finally issued in January 2005, and admits that the cement mills alone are responsible for about 100 times MORE particulate pollution in Rugby than the main stack, which is why the Agency and Rugby Borough Council only wanted the public to look at the main stack emissions.
6. “The highest predicted ground level PM10 concentrations occur due to emissions from the cement mills, due to the HIGH VOLUME of emissions and the number of emissions from this source type.”
7. The Environment Agency had been told this by the CHMRC in an October 2001 report that was kept secret from the public: “Maximum modelled particulate emissions to air from all the cement mills also clearly exceed the benchmark values for air. Although exceedence of these benchmarks alone is not necessarily a cause for concern for the Health Authority as its interest lies in ground level concentrations, the significance of an exceedence of these benchmark standards should nevertheless be considered by the Environment Agency.” They did consider them and decided to hide them!
8. The result was that, in order to gain the IPPC PERMIT, the public were told LIES!!! that the contribution from the whole plant and installation plant was “very small”, and “insignificant” and only added about 0.17 micrograms to long term values of PM10 particulate.

SLOWLY, SLOWLY, SLOWLY, THE TRUTH IS BEING DRAGGED OUT OF ALL THOSE INVOLVED IN THIS WICKED AND HEINOUS ENVIRONMENTAL DISASTER.

Friday, September 01, 2006

CEMEX to produce company accounts

Due on the 3rd October at Warwick Court.

Warwick Court No.2. 25th August : Cemex Committal for Sentence: EA to prosecute Cemex for dumping about 4 tonnes dust on local people/houses/cars up to 4 kilometres away - apparently from an open door on 14th October 2005. Cemex had already owned up at Rugby Magistrate's Court, from where the Case had been transferred for sentencing.

The presiding court recorder was not happy as he had just received an unsigned Witness Statement from Cemex, and an internet printout, a 165 page Bundle, and a new report from Professor Harrison at Birmingham University, and in order to be fair to the Company he needed to call for an adjournment for Cemex to provide company accounts.

He had realised there were NO FINANCIAL ACCOUNTS from Cemex. He said that it could mean great ramifications for the Company, when they could be fined an unlimited substantial penalty. He was adjourning it to received written submissions to keep the court focus.

The Recorder mentioned the Milford Haven and Anglian Water Appeals which had been lodged against an amount which the Companies said they could not pay as they "did not have enough money in their piggy bank." It must be a matter for Cemex to bring their accounts (or their piggy banks) and to do Justice we need as much information as possible.

Lucky for Cemex they had "discovered" in a "cloud of pollution" a healthy defending barrister from under the now defunct Southam Rugby Cement plant, who had lived 20 years in Long Itchington "under Smokey Joe" (as all the children called the Southam cement works), and she, being one of the lucky ones, has not got Asthma.